Girard Avenue over Aramingo Ave(spur A)
GoodPhiladelphia County, Pennsylvania · Nr.Delaware Expy. 3591A05 · Structure no. 000000000038843
- Built
- 1969
- 56 years old, rebuilt 2014
- Condition
- Good
- inspected September 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 457 ft
- 5 main spans
- Daily traffic
- 1,820
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Girard Avenue over Aramingo Ave(spur A) is a steel continuous stringer/multi-beam or girder carrying Girard Avenue over Aramingo Ave(spur A) in Philadelphia County, Pennsylvania. It was built in 1969 and reconstructed in 2014, so it is 56 years old, older than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,820 vehicles a day, roughly 5% of them trucks, projected to reach 3,106 by 2032. The structure is 457 ft (139.3 m) long and 42 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Girard Avenue over Aramingo Ave(spur A) built?
It was built in 1969, making it 56 years old in 2025. It was reconstructed in 2014.
What condition is Girard Avenue over Aramingo Ave(spur A) in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.
How much traffic does Girard Avenue over Aramingo Ave(spur A) carry?
About 1,820 vehicles per day (2024 count), of which roughly 5% are trucks.
How long is Girard Avenue over Aramingo Ave(spur A)?
The structure is 457 ft (139.3 m) long with a longest span of 93 ft (28.3 m) and a deck 42 ft wide.
Who owns Girard Avenue over Aramingo Ave(spur A)?
It is owned by the State Highway Agency.