Girard Avenue over Pile Support Slab
GoodPhiladelphia County, Pennsylvania · Nr.Delaware Expwy 3591A05 · Structure no. 000000000038842
- Built
- 1968
- 57 years old, rebuilt 2014
- Condition
- Good
- inspected September 2024
- Type
- Slab
- Concrete Continuous
- Length
- 225 ft
- 10 main spans
- Daily traffic
- 1,820
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Girard Avenue over Pile Support Slab is a concrete continuous slab carrying Girard Avenue over Pile Support Slab in Philadelphia County, Pennsylvania. It was built in 1968 and reconstructed in 2014, so it is 57 years old, older than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,820 vehicles a day, roughly 5% of them trucks, projected to reach 13,053 by 2032. The structure is 225 ft (68.6 m) long and 45 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Girard Avenue over Pile Support Slab built?
It was built in 1968, making it 57 years old in 2025. It was reconstructed in 2014.
What condition is Girard Avenue over Pile Support Slab in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.
How much traffic does Girard Avenue over Pile Support Slab carry?
About 1,820 vehicles per day (2024 count), of which roughly 5% are trucks.
How long is Girard Avenue over Pile Support Slab?
The structure is 225 ft (68.6 m) long with a longest span of 25 ft (7.6 m) and a deck 45 ft wide.
Who owns Girard Avenue over Pile Support Slab?
It is owned by the State Highway Agency.