US Bridges

N215/5th ST Off Ra over Third ST to N215 on Ramp

Good

San Bernardino County, California · 08-SBD-215-6.98-SBD · Structure no. 54 1251S

Built
2013
12 years old
Condition
Good
inspected February 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete Continuous
Length
673 ft
7 main spans
Daily traffic
4,000
2020 count
Owner
State
State Highway Agency

About this bridge

N215/5th ST Off Ra over Third ST to N215 on Ramp is a prestressed concrete continuous box beam or girders - multiple carrying N215/5th ST Off Ra over Third ST to N215 on Ramp in San Bernardino County, California. It was built in 2013, so it is 12 years old, younger than the California average of 54.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 4,000 vehicles a day, roughly 2% of them trucks, projected to reach 6,063 by 2041. The structure is 673 ft (205 m) long and 38 ft wide. If it were closed, the detour would be 2.5 mi (4 km).

CarriesN215/5th ST Off Ra
CrossesThird ST to N215 on Ramp
Location08-SBD-215-6.98-SBD
RouteInterstate 215
Coordinates34.10538, -117.30178
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionFebruary 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating59.6 US tons
Inventory rating35.7 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans7
Design loadHS 20 + Mod
Structure length673 ft (205 m)
Longest span125 ft (38 m)
Deck width38 ft (11.7 m)
Roadway width35 ft (10.8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic4,000 (2020)
Projected traffic6,063 by 2041
Trucks2%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed2.5 mi (4 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkNon-Interstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was N215/5th ST Off Ra over Third ST to N215 on Ramp built?

It was built in 2013, making it 12 years old in 2025.

What condition is N215/5th ST Off Ra over Third ST to N215 on Ramp in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.

How much traffic does N215/5th ST Off Ra over Third ST to N215 on Ramp carry?

About 4,000 vehicles per day (2020 count), of which roughly 2% are trucks.

How long is N215/5th ST Off Ra over Third ST to N215 on Ramp?

The structure is 673 ft (205 m) long with a longest span of 125 ft (38 m) and a deck 38 ft wide.

Who owns N215/5th ST Off Ra over Third ST to N215 on Ramp?

It is owned by the State Highway Agency.