Lrd Berlin RD over Puchyan River
GoodGreen Lake County, Wisconsin · 0.4M W JCT Sth 49 · Structure no. B24002900000000
- Built
- 2001
- 24 years old
- Condition
- Good
- inspected May 2024
- Type
- Slab
- Concrete
- Length
- 49 ft
- 1 main span
- Daily traffic
- 268
- 2022 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
Lrd Berlin RD over Puchyan River is a concrete slab carrying Lrd Berlin RD over Puchyan River in Green Lake County, Wisconsin. It was built in 2001, so it is 24 years old, younger than the Wisconsin average of 40.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 268 vehicles a day, roughly 3% of them trucks, projected to reach 294 by 2043. The structure is 49 ft (14.8 m) long and 26 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Lrd Berlin RD over Puchyan River built?
It was built in 2001, making it 24 years old in 2025.
What condition is Lrd Berlin RD over Puchyan River in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in May 2024.
How much traffic does Lrd Berlin RD over Puchyan River carry?
About 268 vehicles per day (2022 count), of which roughly 3% are trucks.
How long is Lrd Berlin RD over Puchyan River?
The structure is 49 ft (14.8 m) long with a longest span of 46 ft (14 m) and a deck 26 ft wide.
Who owns Lrd Berlin RD over Puchyan River?
It is owned by the Town or Township Highway Agency.