Hr 8 over Hr 2 & 4 Hr 2 Pedestri
PoorNew York County, New York · 800 Ft So of Gwb · Structure no. 000000005522541
- Built
- 1960
- 65 years old
- Condition
- Poor
- inspected July 2023
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete
- Length
- 677 ft
- 11 main spans
- Daily traffic
- 7,020
- 2020 count
- Owner
- Toll Authority
- Local Toll Authority
About this bridge
Hr 8 over Hr 2 & 4 Hr 2 Pedestri is a prestressed concrete box beam or girders - single or spread carrying Hr 8 over Hr 2 & 4 Hr 2 Pedestri in New York County, New York. It was built in 1960, so it is 65 years old, older than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 7,020 vehicles a day, roughly 8% of them trucks, projected to reach 8,970 by 2041. The structure is 677 ft (206.3 m) long and 35 ft wide.
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Hr 8 over Hr 2 & 4 Hr 2 Pedestri built?
It was built in 1960, making it 65 years old in 2025.
What condition is Hr 8 over Hr 2 & 4 Hr 2 Pedestri in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in July 2023.
How much traffic does Hr 8 over Hr 2 & 4 Hr 2 Pedestri carry?
About 7,020 vehicles per day (2020 count), of which roughly 8% are trucks.
How long is Hr 8 over Hr 2 & 4 Hr 2 Pedestri?
The structure is 677 ft (206.3 m) long with a longest span of 75 ft (22.8 m) and a deck 35 ft wide.
Who owns Hr 8 over Hr 2 & 4 Hr 2 Pedestri?
It is owned by the Local Toll Authority.