US Bridges

NH125 over Axe Handle Brook

Good

Strafford County, New Hampshire · .1 MI from JCT Sp. Tpk. · Structure no. 022201550011000

Built
1983
42 years old, rebuilt 2009
Condition
Good
inspected August 2023
Type
Slab
Concrete
Length
25 ft
1 main span
Daily traffic
16,489
2023 count
Owner
City
City or Municipal Highway Agency

About this bridge

NH125 over Axe Handle Brook is a concrete slab carrying NH125 over Axe Handle Brook in Strafford County, New Hampshire. It was built in 1983 and reconstructed in 2009, so it is 42 years old, younger than the New Hampshire average of 56.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 16,489 vehicles a day, roughly 5% of them trucks, projected to reach 24,403 by 2043. The structure is 25 ft (7.6 m) long and 61 ft wide. If it were closed, the detour would be 3.7 mi (6 km).

CarriesNH125
CrossesAxe Handle Brook
Location.1 MI from JCT Sp. Tpk.
RouteState Highway 125
Coordinates43.2851, -70.97853
Functional classUrban Minor Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection7 GoodSome minor problems.
Last inspectionAugust 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating75.1 US tons
Inventory rating45 US tons

Structure

Structure typeSlab
MaterialConcrete
DeckConcrete, cast-in-place
Main spans1
Design loadHS 25 or greater
Structure length25 ft (7.6 m)
Longest span25 ft (7.6 m)
Deck width61 ft (18.6 m)
Roadway width61 ft (18.6 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic16,489 (2023)
Projected traffic24,403 by 2043
Trucks5%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.7 mi (6 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCity or Municipal Highway Agency
Maintained byCity or Municipal Highway Agency
Historic statusPossibly eligible for the National Register; requires further investigation
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$314,000 (2025 estimate)
NavigationNo navigation control on waterway

Frequently asked questions

When was NH125 over Axe Handle Brook built?

It was built in 1983, making it 42 years old in 2025. It was reconstructed in 2009.

What condition is NH125 over Axe Handle Brook in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.

How much traffic does NH125 over Axe Handle Brook carry?

About 16,489 vehicles per day (2023 count), of which roughly 5% are trucks.

How long is NH125 over Axe Handle Brook?

The structure is 25 ft (7.6 m) long with a longest span of 25 ft (7.6 m) and a deck 61 ft wide.

Who owns NH125 over Axe Handle Brook?

It is owned by the City or Municipal Highway Agency.