FM over Prairie Creek
PoorBenton County, Iowa · 085101005 · Structure no. 000000000072580
- Built
- 1967
- 58 years old
- Condition
- Poor
- inspected April 2024
- Type
- Slab
- Concrete Continuous
- Length
- 128 ft
- 3 main spans
- Daily traffic
- 550
- 2021 count
- Owner
- County
- County Highway Agency
About this bridge
FM over Prairie Creek is a concrete continuous slab carrying FM over Prairie Creek in Benton County, Iowa. It was built in 1967, so it is 58 years old, older than the Iowa average of 45.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 3 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 550 vehicles a day, projected to reach 550 by 2044. The structure is 128 ft (39 m) long and 30 ft wide. If it were closed, the detour would be 5 mi (8 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 3 Serious | Loss of section, deterioration, spalling or scour have seriously affected primary structural components. |
| Superstructure | 3 Serious | Loss of section, deterioration, spalling or scour have seriously affected primary structural components. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was FM over Prairie Creek built?
It was built in 1967, making it 58 years old in 2025.
What condition is FM over Prairie Creek in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in April 2024.
How much traffic does FM over Prairie Creek carry?
About 550 vehicles per day (2021 count).
How long is FM over Prairie Creek?
The structure is 128 ft (39 m) long with a longest span of 49 ft (14.9 m) and a deck 30 ft wide.
Who owns FM over Prairie Creek?
It is owned by the County Highway Agency.