US Bridges

SB I-95 to Griffin over I-595 to SB I-95 Ramp

Good

Broward County, Florida · I95/I595 Interchange · Structure no. 860547

Built
1988
37 years old
Condition
Good
inspected February 2024
Type
Box Beam or Girders - Single or Spread
Steel Continuous
Length
389 ft
3 main spans
Daily traffic
7,600
2024 count
Owner
State
State Highway Agency

About this bridge

SB I-95 to Griffin over I-595 to SB I-95 Ramp is a steel continuous box beam or girders - single or spread carrying SB I-95 to Griffin over I-595 to SB I-95 Ramp in Broward County, Florida. It was built in 1988, so it is 37 years old, younger than the Florida average of 41.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 7,600 vehicles a day, roughly 6% of them trucks, projected to reach 13,186 by 2042. The structure is 389 ft (118.5 m) long and 30 ft wide. If it were closed, the detour would be 1.9 mi (3 km).

CarriesSB I-95 to Griffin
CrossesI-595 to SB I-95 Ramp
LocationI95/I595 Interchange
RouteInterstate 95
StateFlorida
Coordinates26.07313, -80.16801
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure8 Very GoodNo problems noted.
Last inspectionFebruary 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating68.8 US tons
Inventory rating41 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20
Structure length389 ft (118.5 m)
Longest span184 ft (56 m)
Deck width30 ft (9.1 m)
Roadway width27 ft (8.2 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic7,600 (2024)
Projected traffic13,186 by 2042
Trucks6%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.9 mi (3 km)
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was SB I-95 to Griffin over I-595 to SB I-95 Ramp built?

It was built in 1988, making it 37 years old in 2025.

What condition is SB I-95 to Griffin over I-595 to SB I-95 Ramp in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.

How much traffic does SB I-95 to Griffin over I-595 to SB I-95 Ramp carry?

About 7,600 vehicles per day (2024 count), of which roughly 6% are trucks.

How long is SB I-95 to Griffin over I-595 to SB I-95 Ramp?

The structure is 389 ft (118.5 m) long with a longest span of 184 ft (56 m) and a deck 30 ft wide.

Who owns SB I-95 to Griffin over I-595 to SB I-95 Ramp?

It is owned by the State Highway Agency.