W Gutierrez Street over Mission Creek
GoodSanta Barbara County, California · De LA Vina ST /Chapala ST · Structure no. 51C0374
- Built
- 2019
- 6 years old
- Condition
- Good
- inspected February 2022
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 56 ft
- 1 main span
- Daily traffic
- 4,800
- 2015 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
W Gutierrez Street over Mission Creek is a prestressed concrete stringer/multi-beam or girder carrying W Gutierrez Street over Mission Creek in Santa Barbara County, California. It was built in 2019, so it is 6 years old, younger than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 4,800 vehicles a day, roughly 1% of them trucks, projected to reach 5,448 by 2044. The structure is 56 ft (17 m) long and 47 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was W Gutierrez Street over Mission Creek built?
It was built in 2019, making it 6 years old in 2025.
What condition is W Gutierrez Street over Mission Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2022.
How much traffic does W Gutierrez Street over Mission Creek carry?
About 4,800 vehicles per day (2015 count), of which roughly 1% are trucks.
How long is W Gutierrez Street over Mission Creek?
The structure is 56 ft (17 m) long with a longest span of 53 ft (16.2 m) and a deck 47 ft wide.
Who owns W Gutierrez Street over Mission Creek?
It is owned by the City or Municipal Highway Agency.