SR 202L WB over Ramp B(52nd ST Off Ramp)
GoodMaricopa County, Arizona · 3.89 MI E JCT I 10 & · Structure no. 02209
- Built
- 1992
- 33 years old
- Condition
- Good
- inspected November 2024
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete Continuous
- Length
- 154 ft
- 3 main spans
- Daily traffic
- 80,163
- 2022 count
- Owner
- State
- State Highway Agency
About this bridge
SR 202L WB over Ramp B(52nd ST Off Ramp) is a prestressed concrete continuous box beam or girders - single or spread carrying SR 202L WB over Ramp B(52nd ST Off Ramp) in Maricopa County, Arizona. It was built in 1992, so it is 33 years old, younger than the Arizona average of 47.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 80,163 vehicles a day, roughly 6% of them trucks, projected to reach 80,173 by 2042. The structure is 154 ft (46.9 m) long and 71 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was SR 202L WB over Ramp B(52nd ST Off Ramp) built?
It was built in 1992, making it 33 years old in 2025.
What condition is SR 202L WB over Ramp B(52nd ST Off Ramp) in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2024.
How much traffic does SR 202L WB over Ramp B(52nd ST Off Ramp) carry?
About 80,163 vehicles per day (2022 count), of which roughly 6% are trucks.
How long is SR 202L WB over Ramp B(52nd ST Off Ramp)?
The structure is 154 ft (46.9 m) long with a longest span of 70 ft (21.3 m) and a deck 71 ft wide.
Who owns SR 202L WB over Ramp B(52nd ST Off Ramp)?
It is owned by the State Highway Agency.