US 2 over Ebey Slough Drainage
GoodSnohomish County, Washington · 2.2 E JCT I-5 · Structure no. 0013995C0000000
- Built
- 1993
- 32 years old
- Condition
- Good
- inspected April 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete Continuous
- Length
- 939 ft
- 4 main spans
- Daily traffic
- 25,648
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
US 2 over Ebey Slough Drainage is a prestressed concrete continuous box beam or girders - multiple carrying US 2 over Ebey Slough Drainage in Snohomish County, Washington. It was built in 1993, so it is 32 years old, younger than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 25,648 vehicles a day, roughly 5% of them trucks, projected to reach 36,994 by 2039. The structure is 939 ft (286.2 m) long and 43 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was US 2 over Ebey Slough Drainage built?
It was built in 1993, making it 32 years old in 2025.
What condition is US 2 over Ebey Slough Drainage in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.
How much traffic does US 2 over Ebey Slough Drainage carry?
About 25,648 vehicles per day (2023 count), of which roughly 5% are trucks.
How long is US 2 over Ebey Slough Drainage?
The structure is 939 ft (286.2 m) long with a longest span of 166 ft (50.6 m) and a deck 43 ft wide.
Who owns US 2 over Ebey Slough Drainage?
It is owned by the State Highway Agency.