Clear Creek RD NW over SR 3 Access - Luoto Road
GoodKitsap County, Washington · 0.3 W SR 3 · Structure no. 0011864B0000000
- Built
- 1981
- 44 years old
- Condition
- Good
- inspected April 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 203 ft
- 1 main span
- Daily traffic
- 3,389
- 2002 count
- Owner
- State
- State Highway Agency
About this bridge
Clear Creek RD NW over SR 3 Access - Luoto Road is a prestressed concrete stringer/multi-beam or girder carrying Clear Creek RD NW over SR 3 Access - Luoto Road in Kitsap County, Washington. It was built in 1981, so it is 44 years old, younger than the Washington average of 49.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 3,389 vehicles a day, roughly 10% of them trucks, projected to reach 6,154 by 2036. The structure is 203 ft (61.9 m) long and 37 ft wide.
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Clear Creek RD NW over SR 3 Access - Luoto Road built?
It was built in 1981, making it 44 years old in 2025.
What condition is Clear Creek RD NW over SR 3 Access - Luoto Road in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2023.
How much traffic does Clear Creek RD NW over SR 3 Access - Luoto Road carry?
About 3,389 vehicles per day (2002 count), of which roughly 10% are trucks.
How long is Clear Creek RD NW over SR 3 Access - Luoto Road?
The structure is 203 ft (61.9 m) long with a longest span of 140 ft (42.7 m) and a deck 37 ft wide.
Who owns Clear Creek RD NW over SR 3 Access - Luoto Road?
It is owned by the State Highway Agency.