US Bridges

C3010 over Shepard Brook

Good

Washington County, Vermont · 0.25 MI to JCT W CL2 TH1 · Structure no. 101208001912081

Built
1963
62 years old
Condition
Good
inspected August 2024
Type
Stringer/Multi-beam or Girder
Steel
Length
51 ft
1 main span
Daily traffic
50
2019 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

C3010 over Shepard Brook is a steel stringer/multi-beam or girder carrying C3010 over Shepard Brook in Washington County, Vermont. It was built in 1963, so it is 62 years old, older than the Vermont average of 60.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: open, temporary structure in place while original is closed.

It carries about 50 vehicles a day, roughly 2% of them trucks, projected to reach 53 by 2029. The structure is 51 ft (15.5 m) long and 15 ft wide. If it were closed, the detour would be 98.8 mi (159 km).

CarriesC3010
CrossesShepard Brook
Location0.25 MI to JCT W CL2 TH1
StateVermont
Coordinates44.23835, -72.83871
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure7 GoodSome minor problems.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionAugust 2024
Inspection intervalevery 24 months
Operating statusOpen, temporary structure in place while original is closed
ScourScour critical; foundations unstable for calculated scour conditions
Structural evaluation3: Basically intolerable, requiring high priority of corrective action
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy6: Equal to present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating0 US tons
Inventory rating0 US tons

Structure

MaterialSteel
DeckConcrete, cast-in-place
Main spans1
Design loadHS 20
Structure length51 ft (15.5 m)
Longest span43 ft (13.1 m)
Deck width15 ft (4.7 m)
Roadway width13 ft (4.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic50 (2019)
Projected traffic53 by 2029
Trucks2%
Lanes on structure1
Traffic directionOne-lane bridge for two-way traffic
CarriesHighway
CrossesWaterway
Detour if closed98.8 mi (159 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was C3010 over Shepard Brook built?

It was built in 1963, making it 62 years old in 2025.

What condition is C3010 over Shepard Brook in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.

How much traffic does C3010 over Shepard Brook carry?

About 50 vehicles per day (2019 count), of which roughly 2% are trucks.

How long is C3010 over Shepard Brook?

The structure is 51 ft (15.5 m) long with a longest span of 43 ft (13.1 m) and a deck 15 ft wide.

Who owns C3010 over Shepard Brook?

It is owned by the Town or Township Highway Agency.