- Built
- 1964
- 61 years old, rebuilt 1999
- Condition
- Good
- inspected June 2024
- Type
- Slab
- Prestressed Concrete
- Length
- 45 ft
- 1 main span
- Daily traffic
- 3,000
- 2016 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
North Branch ST over Furnace Brook is a prestressed concrete slab carrying North Branch ST over Furnace Brook in Bennington County, Vermont. It was built in 1964 and reconstructed in 1999, so it is 61 years old, older than the Vermont average of 60.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 3,000 vehicles a day, roughly 2% of them trucks, projected to reach 3,150 by 2026. The structure is 45 ft (13.7 m) long and 28 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was North Branch ST over Furnace Brook built?
It was built in 1964, making it 61 years old in 2025. It was reconstructed in 1999.
What condition is North Branch ST over Furnace Brook in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.
How much traffic does North Branch ST over Furnace Brook carry?
About 3,000 vehicles per day (2016 count), of which roughly 2% are trucks.
How long is North Branch ST over Furnace Brook?
The structure is 45 ft (13.7 m) long with a longest span of 44 ft (13.4 m) and a deck 28 ft wide.
Who owns North Branch ST over Furnace Brook?
It is owned by the Town or Township Highway Agency.