US Bridges

SR-85 (mvc) NB over SR-201

Good

Salt Lake County, Utah · SR-85 (mvc) over SR-201 · Structure no. 1F 916

Built
2021
4 years old
Condition
Good
inspected November 2022
Type
Stringer/Multi-beam or Girder
Concrete
Length
219 ft
2 main spans
Daily traffic
11,420
2023 count
Owner
State
State Highway Agency

About this bridge

SR-85 (mvc) NB over SR-201 is a concrete stringer/multi-beam or girder carrying SR-85 (mvc) NB over SR-201 in Salt Lake County, Utah. It was built in 2021, so it is 4 years old, younger than the Utah average of 40.1 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 11,420 vehicles a day, roughly 16% of them trucks, projected to reach 13,704 by 2043. The structure is 219 ft (66.8 m) long and 79 ft wide. If it were closed, the detour would be 5 mi (8 km).

CarriesSR-85 (mvc) NB
CrossesSR-201
LocationSR-85 (mvc) over SR-201
RouteState Highway 85
StateUtah
Coordinates40.72555, -112.02899
Functional classUrban Other Principal Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure8 Very GoodNo problems noted.
Substructure7 GoodSome minor problems.
Last inspectionNovember 2022
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating46.4 US tons
Inventory rating35.7 US tons

Structure

MaterialConcrete
DeckConcrete, cast-in-place
Main spans2
Design loadHL 93
Structure length219 ft (66.8 m)
Longest span129 ft (39.4 m)
Deck width79 ft (24 m)
Roadway width76 ft (23.2 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic11,420 (2023)
Projected traffic13,704 by 2043
Trucks16%
Lanes on structure3
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed5 mi (8 km)
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was SR-85 (mvc) NB over SR-201 built?

It was built in 2021, making it 4 years old in 2025.

What condition is SR-85 (mvc) NB over SR-201 in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2022.

How much traffic does SR-85 (mvc) NB over SR-201 carry?

About 11,420 vehicles per day (2023 count), of which roughly 16% are trucks.

How long is SR-85 (mvc) NB over SR-201?

The structure is 219 ft (66.8 m) long with a longest span of 129 ft (39.4 m) and a deck 79 ft wide.

Who owns SR-85 (mvc) NB over SR-201?

It is owned by the State Highway Agency.