US Bridges

Terminal Drive over Slc Airport Terminal

Good

Salt Lake County, Utah · Slc Airport Terminal · Structure no. 035252F

Built
2020
5 years old
Condition
Good
inspected January 2024
Type
Stringer/Multi-beam or Girder
Prestressed Concrete
Length
2,025 ft
19 main spans
Daily traffic
23,000
2019 count
Owner
City
City or Municipal Highway Agency

About this bridge

Terminal Drive over Slc Airport Terminal is a prestressed concrete stringer/multi-beam or girder carrying Terminal Drive over Slc Airport Terminal in Salt Lake County, Utah. It was built in 2020, so it is 5 years old, younger than the Utah average of 40.1 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 23,000 vehicles a day, roughly 1% of them trucks, projected to reach 288,750 by 2039. The structure is 2,025 ft (617.2 m) long and 39 ft wide.

CarriesTerminal Drive
CrossesSlc Airport Terminal
LocationSlc Airport Terminal
RouteCity Street 2370
StateUtah
Coordinates40.78417, -111.98227
Functional classRural Principal Arterial - Other

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionJanuary 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry6: Equal to present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating53.6 US tons
Inventory rating42.9 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans19
Design loadHL 93
Structure length2,025 ft (617.2 m)
Longest span112 ft (34 m)
Deck width39 ft (11.9 m)
Roadway width36 ft (11 m)
Vertical clearance over deck100 ft (30.5 m)

Traffic and service

Average daily traffic23,000 (2019)
Projected traffic288,750 by 2039
Trucks1%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed—
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerCity or Municipal Highway Agency
Maintained byCity or Municipal Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was Terminal Drive over Slc Airport Terminal built?

It was built in 2020, making it 5 years old in 2025.

What condition is Terminal Drive over Slc Airport Terminal in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in January 2024.

How much traffic does Terminal Drive over Slc Airport Terminal carry?

About 23,000 vehicles per day (2019 count), of which roughly 1% are trucks.

How long is Terminal Drive over Slc Airport Terminal?

The structure is 2,025 ft (617.2 m) long with a longest span of 112 ft (34 m) and a deck 39 ft wide.

Who owns Terminal Drive over Slc Airport Terminal?

It is owned by the City or Municipal Highway Agency.