Mile 19 N RD over N Main Drainage Ditch
FairHidalgo County, Texas · 1.25 MI E of FM 493 · Structure no. 211090AA0296003
- Built
- 1985
- 40 years old
- Condition
- Fair
- inspected June 2024
- Type
- Stringer/Multi-beam or Girder
- Concrete
- Length
- 93 ft
- 3 main spans
- Daily traffic
- 495
- 2022 count
- Owner
- County
- County Highway Agency
About this bridge
Mile 19 N RD over N Main Drainage Ditch is a concrete stringer/multi-beam or girder carrying Mile 19 N RD over N Main Drainage Ditch in Hidalgo County, Texas. It was built in 1985, so it is 40 years old, younger than the Texas average of 44.4 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 495 vehicles a day, roughly 8% of them trucks, projected to reach 330 by 2030. The structure is 93 ft (28.3 m) long and 28 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Mile 19 N RD over N Main Drainage Ditch built?
It was built in 1985, making it 40 years old in 2025.
What condition is Mile 19 N RD over N Main Drainage Ditch in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2024.
How much traffic does Mile 19 N RD over N Main Drainage Ditch carry?
About 495 vehicles per day (2022 count), of which roughly 8% are trucks.
How long is Mile 19 N RD over N Main Drainage Ditch?
The structure is 93 ft (28.3 m) long with a longest span of 30 ft (9.2 m) and a deck 28 ft wide.
Who owns Mile 19 N RD over N Main Drainage Ditch?
It is owned by the County Highway Agency.