Pr 155 49.8 KM over Morovis River
PoorMorovis Municipio, Puerto Rico · 2 KM Northwest of Morovis · Structure no. 003351
- Built
- 1914
- 111 years old
- Condition
- Poor
- inspected March 2025
- Type
- Girder and Floorbeam System
- Steel
- Length
- 75 ft
- 1 main span
- Daily traffic
- 7,200
- 2017 count
- Owner
- State
- State Highway Agency
About this bridge
Pr 155 49.8 KM over Morovis River is a steel girder and floorbeam system carrying Pr 155 49.8 KM over Morovis River in Morovis Municipio, Puerto Rico. It was built in 1914, so it is 111 years old, older than the Puerto Rico average of 51.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: open, temporary structure in place while original is closed.
It carries about 7,200 vehicles a day, roughly 4% of them trucks, projected to reach 9,400 by 2025. The structure is 75 ft (22.8 m) long and 20 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Pr 155 49.8 KM over Morovis River built?
It was built in 1914, making it 111 years old in 2025.
What condition is Pr 155 49.8 KM over Morovis River in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in March 2025.
How much traffic does Pr 155 49.8 KM over Morovis River carry?
About 7,200 vehicles per day (2017 count), of which roughly 4% are trucks.
How long is Pr 155 49.8 KM over Morovis River?
The structure is 75 ft (22.8 m) long with a longest span of 75 ft (22.8 m) and a deck 20 ft wide.
Who owns Pr 155 49.8 KM over Morovis River?
It is owned by the State Highway Agency.