US Bridges

Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM

Fair

Juana Diaz Municipio, Puerto Rico · 2 KM South of Juana Diaz · Structure no. 011462

Built
1971
54 years old
Condition
Fair
inspected March 2024
Type
Stringer/Multi-beam or Girder
Prestressed Concrete
Length
98 ft
1 main span
Daily traffic
17,900
2017 count
Owner
Toll Authority
State Toll Authority

About this bridge

Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM is a prestressed concrete stringer/multi-beam or girder carrying Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM in Juana Diaz Municipio, Puerto Rico. It was built in 1971, so it is 54 years old, older than the Puerto Rico average of 51.2 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 17,900 vehicles a day, roughly 5% of them trucks, projected to reach 25,050 by 2025. The structure is 98 ft (29.9 m) long and 47 ft wide. If it were closed, the detour would be 0.6 mi (1 km).

CarriesPr 52 Nobd 90.7 KM
CrossesPr 582 0.8 KM
Location2 KM South of Juana Diaz
RouteInterstate 52
Coordinates18.04264, -66.50567
Functional classRural Principal Arterial - Interstate

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Superstructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionMarch 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating55.4 US tons
Inventory rating34.3 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans1
Design loadHS 20
Structure length98 ft (29.9 m)
Longest span98 ft (29.9 m)
Deck width47 ft (14.3 m)
Roadway width41 ft (12.4 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic17,900 (2017)
Projected traffic25,050 by 2025
Trucks5%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed0.6 mi (1 km)
TollOn a toll road
National Highway SystemYes

Ownership and planned work

OwnerState Toll Authority
Maintained byState Toll Authority
Historic statusNot eligible for the National Register of Historic Places
Work proposedRehabilitation because of general structure deterioration or inadequate strength
Estimated improvement cost$102,000 (2018 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM built?

It was built in 1971, making it 54 years old in 2025.

What condition is Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in March 2024.

How much traffic does Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM carry?

About 17,900 vehicles per day (2017 count), of which roughly 5% are trucks.

How long is Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM?

The structure is 98 ft (29.9 m) long with a longest span of 98 ft (29.9 m) and a deck 47 ft wide.

Who owns Pr 52 Nobd 90.7 KM over Pr 582 0.8 KM?

It is owned by the State Toll Authority.