Pr 123 67.0 KM over El Jobo Creek
PoorArecibo Municipio, Puerto Rico · 12 KM North of Utuado · Structure no. 001621
- Built
- 1940
- 85 years old
- Condition
- Poor
- inspected October 2024
- Type
- Slab
- Concrete Continuous
- Length
- 131 ft
- 6 main spans
- Daily traffic
- 1,100
- 2017 count
- Owner
- State
- State Highway Agency
About this bridge
Pr 123 67.0 KM over El Jobo Creek is a concrete continuous slab carrying Pr 123 67.0 KM over El Jobo Creek in Arecibo Municipio, Puerto Rico. It was built in 1940, so it is 85 years old, older than the Puerto Rico average of 51.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 3 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: open, posting recommended but not legally implemented.
It carries about 1,100 vehicles a day, roughly 4% of them trucks, projected to reach 1,500 by 2025. The structure is 131 ft (39.9 m) long and 23 ft wide. If it were closed, the detour would be 16.2 mi (26 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 3 Serious | Loss of section, deterioration, spalling or scour have seriously affected primary structural components. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Pr 123 67.0 KM over El Jobo Creek built?
It was built in 1940, making it 85 years old in 2025.
What condition is Pr 123 67.0 KM over El Jobo Creek in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in October 2024.
How much traffic does Pr 123 67.0 KM over El Jobo Creek carry?
About 1,100 vehicles per day (2017 count), of which roughly 4% are trucks.
How long is Pr 123 67.0 KM over El Jobo Creek?
The structure is 131 ft (39.9 m) long with a longest span of 23 ft (6.9 m) and a deck 23 ft wide.
Who owns Pr 123 67.0 KM over El Jobo Creek?
It is owned by the State Highway Agency.