Ramp D (sb) over Aramingo Av/Conrail/Crk.
GoodPhiladelphia County, Pennsylvania · (bri) Ramp D 3591G01 · Structure no. 000000000040477
- Built
- 1999
- 26 years old, rebuilt 2024
- Condition
- Good
- inspected February 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 1,435 ft
- 11 main spans
- Daily traffic
- 10,471
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Ramp D (sb) over Aramingo Av/Conrail/Crk. is a steel stringer/multi-beam or girder carrying Ramp D (sb) over Aramingo Av/Conrail/Crk. in Philadelphia County, Pennsylvania. It was built in 1999 and reconstructed in 2024, so it is 26 years old, younger than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 10,471 vehicles a day, roughly 7% of them trucks, projected to reach 12,124 by 2032. The structure is 1,435 ft (437.4 m) long and 49 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ramp D (sb) over Aramingo Av/Conrail/Crk. built?
It was built in 1999, making it 26 years old in 2025. It was reconstructed in 2024.
What condition is Ramp D (sb) over Aramingo Av/Conrail/Crk. in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.
How much traffic does Ramp D (sb) over Aramingo Av/Conrail/Crk. carry?
About 10,471 vehicles per day (2024 count), of which roughly 7% are trucks.
How long is Ramp D (sb) over Aramingo Av/Conrail/Crk.?
The structure is 1,435 ft (437.4 m) long with a longest span of 195 ft (59.4 m) and a deck 49 ft wide.
Who owns Ramp D (sb) over Aramingo Av/Conrail/Crk.?
It is owned by the State Highway Agency.