P-Town X-Way (eb) over Upper Indian Head Road
GoodMontgomery County, Pennsylvania · N. of Oaks 27D3/3253H8 · Structure no. 000000000027441
- Built
- 1984
- 41 years old
- Condition
- Good
- inspected December 2022
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 159 ft
- 3 main spans
- Daily traffic
- 34,138
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
P-Town X-Way (eb) over Upper Indian Head Road is a prestressed concrete stringer/multi-beam or girder carrying P-Town X-Way (eb) over Upper Indian Head Road in Montgomery County, Pennsylvania. It was built in 1984, so it is 41 years old, younger than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 34,138 vehicles a day, roughly 5% of them trucks, projected to reach 35,777 by 2032. The structure is 159 ft (48.5 m) long and 46 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was P-Town X-Way (eb) over Upper Indian Head Road built?
It was built in 1984, making it 41 years old in 2025.
What condition is P-Town X-Way (eb) over Upper Indian Head Road in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2022.
How much traffic does P-Town X-Way (eb) over Upper Indian Head Road carry?
About 34,138 vehicles per day (2024 count), of which roughly 5% are trucks.
How long is P-Town X-Way (eb) over Upper Indian Head Road?
The structure is 159 ft (48.5 m) long with a longest span of 76 ft (23.2 m) and a deck 46 ft wide.
Who owns P-Town X-Way (eb) over Upper Indian Head Road?
It is owned by the State Highway Agency.