T-337 Strauser RD over Red Bank Creek
GoodJefferson County, Pennsylvania · 0.1 Miles SW of SR 3007 · Structure no. 000000000040723
- Built
- 1999
- 26 years old
- Condition
- Good
- inspected August 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete Continuous
- Length
- 244 ft
- 3 main spans
- Daily traffic
- 250
- 2021 count
- Owner
- County
- County Highway Agency
About this bridge
T-337 Strauser RD over Red Bank Creek is a prestressed concrete continuous box beam or girders - multiple carrying T-337 Strauser RD over Red Bank Creek in Jefferson County, Pennsylvania. It was built in 1999, so it is 26 years old, younger than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 250 vehicles a day, roughly 9% of them trucks, projected to reach 320 by 2041. The structure is 244 ft (74.4 m) long and 31 ft wide. If it were closed, the detour would be 6.2 mi (10 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was T-337 Strauser RD over Red Bank Creek built?
It was built in 1999, making it 26 years old in 2025.
What condition is T-337 Strauser RD over Red Bank Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does T-337 Strauser RD over Red Bank Creek carry?
About 250 vehicles per day (2021 count), of which roughly 9% are trucks.
How long is T-337 Strauser RD over Red Bank Creek?
The structure is 244 ft (74.4 m) long with a longest span of 81 ft (24.7 m) and a deck 31 ft wide.
Who owns T-337 Strauser RD over Red Bank Creek?
It is owned by the County Highway Agency.