Ramp I over Mcknight Interchange
GoodAllegheny County, Pennsylvania · Ramp I-Over Evergreen RD · Structure no. 000000000002916
- Built
- 1986
- 39 years old
- Condition
- Good
- inspected April 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 247 ft
- 3 main spans
- Daily traffic
- 15,036
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Ramp I over Mcknight Interchange is a steel continuous stringer/multi-beam or girder carrying Ramp I over Mcknight Interchange in Allegheny County, Pennsylvania. It was built in 1986, so it is 39 years old, younger than the Pennsylvania average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 15,036 vehicles a day, roughly 7% of them trucks, projected to reach 14,235 by 2032. The structure is 247 ft (75.3 m) long and 36 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ramp I over Mcknight Interchange built?
It was built in 1986, making it 39 years old in 2025.
What condition is Ramp I over Mcknight Interchange in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.
How much traffic does Ramp I over Mcknight Interchange carry?
About 15,036 vehicles per day (2024 count), of which roughly 7% are trucks.
How long is Ramp I over Mcknight Interchange?
The structure is 247 ft (75.3 m) long with a longest span of 93 ft (28.3 m) and a deck 36 ft wide.
Who owns Ramp I over Mcknight Interchange?
It is owned by the State Highway Agency.