US Bridges

S.H. 7 over Guy Sandy Creek

Fair

Murray County, Oklahoma · 4.9 MI E JCT US 77 · Structure no. 194890000000000

Built
1978
47 years old
Condition
Fair
inspected March 2024
Type
Stringer/Multi-beam or Girder
Prestressed Concrete
Length
212 ft
3 main spans
Daily traffic
5,200
2022 count
Owner
State
State Highway Agency

About this bridge

S.H. 7 over Guy Sandy Creek is a prestressed concrete stringer/multi-beam or girder carrying S.H. 7 over Guy Sandy Creek in Murray County, Oklahoma. It was built in 1978, so it is 47 years old, younger than the Oklahoma average of 47.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 5,200 vehicles a day, roughly 25% of them trucks, projected to reach 8,320 by 2042. The structure is 212 ft (64.6 m) long and 44 ft wide.

CarriesS.H. 7
CrossesGuy Sandy Creek
Location4.9 MI E JCT US 77
RouteState Highway 7
Coordinates34.50635, -97.03397
Functional classRural Principal Arterial - Other

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionMarch 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation6: Equal to present minimum criteria
Deck geometry7: Better than present minimum criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating50 US tons
Inventory rating30 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20
Structure length212 ft (64.6 m)
Longest span80 ft (24.4 m)
Deck width44 ft (13.3 m)
Roadway width41 ft (12.4 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic5,200 (2022)
Projected traffic8,320 by 2042
Trucks25%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesWaterway
Detour if closed—
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$2.1 million
NavigationNo navigation control on waterway

Frequently asked questions

When was S.H. 7 over Guy Sandy Creek built?

It was built in 1978, making it 47 years old in 2025.

What condition is S.H. 7 over Guy Sandy Creek in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in March 2024.

How much traffic does S.H. 7 over Guy Sandy Creek carry?

About 5,200 vehicles per day (2022 count), of which roughly 25% are trucks.

How long is S.H. 7 over Guy Sandy Creek?

The structure is 212 ft (64.6 m) long with a longest span of 80 ft (24.4 m) and a deck 44 ft wide.

Who owns S.H. 7 over Guy Sandy Creek?

It is owned by the State Highway Agency.