I.R. 271 over IR271SB over I-77NB Ramp
GoodSummit County, Ohio · JCT of Ir 271 and Ir 77 · Structure no. 7708912
- Built
- 1971
- 54 years old
- Condition
- Good
- inspected December 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 128 ft
- 3 main spans
- Daily traffic
- 15,624
- 2015 count
- Owner
- State
- State Highway Agency
About this bridge
I.R. 271 over IR271SB over I-77NB Ramp is a steel continuous stringer/multi-beam or girder carrying I.R. 271 over IR271SB over I-77NB Ramp in Summit County, Ohio. It was built in 1971, so it is 54 years old, older than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 15,624 vehicles a day, roughly 17% of them trucks, projected to reach 21,686 by 2035. The structure is 128 ft (39 m) long and 42 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I.R. 271 over IR271SB over I-77NB Ramp built?
It was built in 1971, making it 54 years old in 2025.
What condition is I.R. 271 over IR271SB over I-77NB Ramp in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2024.
How much traffic does I.R. 271 over IR271SB over I-77NB Ramp carry?
About 15,624 vehicles per day (2015 count), of which roughly 17% are trucks.
How long is I.R. 271 over IR271SB over I-77NB Ramp?
The structure is 128 ft (39 m) long with a longest span of 49 ft (14.9 m) and a deck 42 ft wide.
Who owns I.R. 271 over IR271SB over I-77NB Ramp?
It is owned by the State Highway Agency.