Ir 75 over Ramp NB IR280 to SB IR75
GoodLucas County, Ohio · Jct. Ir 75 & Ir 280 · Structure no. 4804279
- Built
- 2016
- 9 years old
- Condition
- Good
- inspected October 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 157 ft
- 1 main span
- Daily traffic
- 75,600
- 2017 count
- Owner
- State
- State Highway Agency
About this bridge
Ir 75 over Ramp NB IR280 to SB IR75 is a steel stringer/multi-beam or girder carrying Ir 75 over Ramp NB IR280 to SB IR75 in Lucas County, Ohio. It was built in 2016, so it is 9 years old, younger than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 75,600 vehicles a day, roughly 21% of them trucks, projected to reach 78,299 by 2037. The structure is 157 ft (47.9 m) long and 102 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ir 75 over Ramp NB IR280 to SB IR75 built?
It was built in 2016, making it 9 years old in 2025.
What condition is Ir 75 over Ramp NB IR280 to SB IR75 in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2024.
How much traffic does Ir 75 over Ramp NB IR280 to SB IR75 carry?
About 75,600 vehicles per day (2017 count), of which roughly 21% are trucks.
How long is Ir 75 over Ramp NB IR280 to SB IR75?
The structure is 157 ft (47.9 m) long with a longest span of 150 ft (45.7 m) and a deck 102 ft wide.
Who owns Ir 75 over Ramp NB IR280 to SB IR75?
It is owned by the State Highway Agency.