Ramp E to Airport over Road E over I670

Good

Franklin County, Ohio · 1.38 MI W of IR270 · Structure no. 2517957

Built
1990
35 years old
Condition
Good
inspected November 2023
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
436 ft
6 main spans
Daily traffic
111,420
2010 count
Owner
State
State Highway Agency

About this bridge

Ramp E to Airport over Road E over I670 is a steel continuous stringer/multi-beam or girder carrying Ramp E to Airport over Road E over I670 in Franklin County, Ohio. It was built in 1990, so it is 35 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 111,420 vehicles a day, roughly 3% of them trucks, projected to reach 155,888 by 2030. The structure is 436 ft (132.9 m) long and 33 ft wide. If it were closed, the detour would be 3.1 mi (5 km).

CarriesRamp E to Airport
CrossesRoad E over I670
Location1.38 MI W of IR270
RouteInterstate 670
StateOhio
Coordinates40.00175, -82.92211
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure8 Very GoodNo problems noted.
Last inspectionNovember 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation4: Meets minimum tolerable limits to be left in place as is
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating25 US tons
Inventory rating17.9 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans6
Design loadHS 20 + Mod
Structure length436 ft (132.9 m)
Longest span97 ft (29.6 m)
Deck width33 ft (10 m)
Roadway width29 ft (8.8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic111,420 (2010)
Projected traffic155,888 by 2030
Trucks3%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed3.1 mi (5 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was Ramp E to Airport over Road E over I670 built?

It was built in 1990, making it 35 years old in 2025.

What condition is Ramp E to Airport over Road E over I670 in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.

How much traffic does Ramp E to Airport over Road E over I670 carry?

About 111,420 vehicles per day (2010 count), of which roughly 3% are trucks.

How long is Ramp E to Airport over Road E over I670?

The structure is 436 ft (132.9 m) long with a longest span of 97 ft (29.6 m) and a deck 33 ft wide.

Who owns Ramp E to Airport over Road E over I670?

It is owned by the State Highway Agency.