Onondaga County, New York · 1.1 MI E I90 Exit 36 Ramp · Structure no. 000000001049830

Built
2004
21 years old
Condition
Good
inspected September 2023
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
201 ft
2 main spans
Daily traffic
8,922
2021 count
Owner
Toll Authority
State Toll Authority

About this bridge

Lemoyne Ave over 90IX RTE I90 is a steel continuous stringer/multi-beam or girder carrying Lemoyne Ave over 90IX RTE I90 in Onondaga County, New York. It was built in 2004, so it is 21 years old, younger than the New York average of 53 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 8,922 vehicles a day, roughly 3% of them trucks, projected to reach 10,838 by 2041. The structure is 201 ft (61.3 m) long and 70 ft wide. If it were closed, the detour would be 0.6 mi (1 km).

CarriesLemoyne Ave
Crosses90IX RTE I90
Location1.1 MI E I90 Exit 36 Ramp
RouteCounty Highway 0
Coordinates43.09212, -76.14529
Functional classUrban Minor Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure9 ExcellentNo problems noted.
Substructure8 Very GoodNo problems noted.
Last inspectionSeptember 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation8: Equal to present desirable criteria
Deck geometry7: Better than present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating60.4 US tons
Inventory rating46.4 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans2
Design loadHS 25 or greater
Structure length201 ft (61.3 m)
Longest span100 ft (30.5 m)
Deck width70 ft (21.4 m)
Roadway width52 ft (15.8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic8,922 (2021)
Projected traffic10,838 by 2041
Trucks3%
Lanes on structure3
Traffic directionTwo-way traffic
CarriesHighway and pedestrian
CrossesHighway
Detour if closed0.6 mi (1 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Toll Authority
Maintained byState Toll Authority
Historic statusHistorical significance not determinable at this time
Work proposedWidening with deck rehabilitation or replacement
Estimated improvement cost$4.7 million (2024 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was Lemoyne Ave over 90IX RTE I90 built?

It was built in 2004, making it 21 years old in 2025.

What condition is Lemoyne Ave over 90IX RTE I90 in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2023.

How much traffic does Lemoyne Ave over 90IX RTE I90 carry?

About 8,922 vehicles per day (2021 count), of which roughly 3% are trucks.

How long is Lemoyne Ave over 90IX RTE I90?

The structure is 201 ft (61.3 m) long with a longest span of 100 ft (30.5 m) and a deck 70 ft wide.

Who owns Lemoyne Ave over 90IX RTE I90?

It is owned by the State Toll Authority.