RTE 251 over 390I390I43031047 RTE I3
PoorMonroe County, New York · 0.2MI.W.JCT.RTS. 251 & 15 · Structure no. 000000001069040
- Built
- 1976
- 49 years old
- Condition
- Poor
- inspected August 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 294 ft
- 2 main spans
- Daily traffic
- 3,495
- 2021 count
- Owner
- State
- State Highway Agency
About this bridge
RTE 251 over 390I390I43031047 RTE I3 is a steel continuous stringer/multi-beam or girder carrying RTE 251 over 390I390I43031047 RTE I3 in Monroe County, New York. It was built in 1976, so it is 49 years old, younger than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 3,495 vehicles a day, roughly 8% of them trucks, projected to reach 3,516 by 2041. The structure is 294 ft (89.6 m) long and 76 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE 251 over 390I390I43031047 RTE I3 built?
It was built in 1976, making it 49 years old in 2025.
What condition is RTE 251 over 390I390I43031047 RTE I3 in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in August 2024.
How much traffic does RTE 251 over 390I390I43031047 RTE I3 carry?
About 3,495 vehicles per day (2021 count), of which roughly 8% are trucks.
How long is RTE 251 over 390I390I43031047 RTE I3?
The structure is 294 ft (89.6 m) long with a longest span of 145 ft (44.1 m) and a deck 76 ft wide.
Who owns RTE 251 over 390I390I43031047 RTE I3?
It is owned by the State Highway Agency.