95S Off R to I15N/ over Rancho Ramp to US95S

Good

Clark County, Nevada · Las Vegas · Structure no. H2710

Built
2007
18 years old
Condition
Good
inspected October 2023
Type
Box Beam or Girders - Single or Spread
Prestressed Concrete Continuous
Length
456 ft
4 main spans
Daily traffic
5,900
2021 count
Owner
State
State Highway Agency

About this bridge

95S Off R to I15N/ over Rancho Ramp to US95S is a prestressed concrete continuous box beam or girders - single or spread carrying 95S Off R to I15N/ over Rancho Ramp to US95S in Clark County, Nevada. It was built in 2007, so it is 18 years old, younger than the Nevada average of 36.4 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 5,900 vehicles a day, roughly 3% of them trucks, projected to reach 10,341 by 2040. The structure is 456 ft (139 m) long and 50 ft wide. If it were closed, the detour would be 1.9 mi (3 km).

Carries95S Off R to I15N/
CrossesRancho Ramp to US95S
LocationLas Vegas
RouteU.S. Route 95
StateNevada
Coordinates36.17555, -115.16977
Functional classUrban Principal Arterial - Other Freeway or Expressway

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Last inspectionOctober 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation8: Equal to present desirable criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating63.7 US tons
Inventory rating46 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans4
Design loadHS 20 + Mod
Structure length456 ft (139 m)
Longest span131 ft (40 m)
Deck width50 ft (15.3 m)
Roadway width47 ft (14.4 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic5,900 (2021)
Projected traffic10,341 by 2040
Trucks3%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed1.9 mi (3 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkNon-Interstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was 95S Off R to I15N/ over Rancho Ramp to US95S built?

It was built in 2007, making it 18 years old in 2025.

What condition is 95S Off R to I15N/ over Rancho Ramp to US95S in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2023.

How much traffic does 95S Off R to I15N/ over Rancho Ramp to US95S carry?

About 5,900 vehicles per day (2021 count), of which roughly 3% are trucks.

How long is 95S Off R to I15N/ over Rancho Ramp to US95S?

The structure is 456 ft (139 m) long with a longest span of 131 ft (40 m) and a deck 50 ft wide.

Who owns 95S Off R to I15N/ over Rancho Ramp to US95S?

It is owned by the State Highway Agency.