I-25 Nbl over Sandia Railroad Spur
GoodBernalillo County, New Mexico · 1.0 M S JCT Rio Bravo · Structure no. 000000000009674
- Built
- 2016
- 9 years old
- Condition
- Good
- inspected January 2025
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete Continuous
- Length
- 132 ft
- 2 main spans
- Daily traffic
- 51,483
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
I-25 Nbl over Sandia Railroad Spur is a prestressed concrete continuous stringer/multi-beam or girder carrying I-25 Nbl over Sandia Railroad Spur in Bernalillo County, New Mexico. It was built in 2016, so it is 9 years old, younger than the New Mexico average of 51.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 51,483 vehicles a day, roughly 14% of them trucks, projected to reach 70,016 by 2043. The structure is 132 ft (40.2 m) long and 63 ft wide.
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I-25 Nbl over Sandia Railroad Spur built?
It was built in 2016, making it 9 years old in 2025.
What condition is I-25 Nbl over Sandia Railroad Spur in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in January 2025.
How much traffic does I-25 Nbl over Sandia Railroad Spur carry?
About 51,483 vehicles per day (2023 count), of which roughly 14% are trucks.
How long is I-25 Nbl over Sandia Railroad Spur?
The structure is 132 ft (40.2 m) long with a longest span of 64 ft (19.4 m) and a deck 63 ft wide.
Who owns I-25 Nbl over Sandia Railroad Spur?
It is owned by the State Highway Agency.