New Cnty RD CR 655 over Main Line M.P. 3.73
GoodHudson County, New Jersey · 0.1MI N of Njtpk Exit 15X · Structure no. 09S9501
- Built
- 2005
- 20 years old
- Condition
- Good
- inspected February 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 140 ft
- 1 main span
- Daily traffic
- 11,305
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
New Cnty RD CR 655 over Main Line M.P. 3.73 is a steel stringer/multi-beam or girder carrying New Cnty RD CR 655 over Main Line M.P. 3.73 in Hudson County, New Jersey. It was built in 2005, so it is 20 years old, younger than the New Jersey average of 58.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 11,305 vehicles a day, roughly 1% of them trucks, projected to reach 15,230 by 2043. The structure is 140 ft (42.7 m) long and 44 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was New Cnty RD CR 655 over Main Line M.P. 3.73 built?
It was built in 2005, making it 20 years old in 2025.
What condition is New Cnty RD CR 655 over Main Line M.P. 3.73 in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.
How much traffic does New Cnty RD CR 655 over Main Line M.P. 3.73 carry?
About 11,305 vehicles per day (2023 count), of which roughly 1% are trucks.
How long is New Cnty RD CR 655 over Main Line M.P. 3.73?
The structure is 140 ft (42.7 m) long with a longest span of 135 ft (41.1 m) and a deck 44 ft wide.
Who owns New Cnty RD CR 655 over Main Line M.P. 3.73?
It is owned by the State Highway Agency.