Taylor CR RD over Grasshopper Creek 004
FairPosted for loadBeaverhead County, Montana · 21M W Dillon · Structure no. L01057000+01001
- Built
- 1986
- 39 years old
- Condition
- Fair
- inspected June 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 26 ft
- 1 main span
- Daily traffic
- 100
- 2025 count
- Owner
- County
- County Highway Agency
About this bridge
Taylor CR RD over Grasshopper Creek 004 is a steel stringer/multi-beam or girder carrying Taylor CR RD over Grasshopper Creek 004 in Beaverhead County, Montana. It was built in 1986, so it is 39 years old, younger than the Montana average of 47 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.
It carries about 100 vehicles a day, roughly 3% of them trucks, projected to reach 100 by 2040. The structure is 26 ft (7.8 m) long and 20 ft wide. If it were closed, the detour would be 14.9 mi (24 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Taylor CR RD over Grasshopper Creek 004 built?
It was built in 1986, making it 39 years old in 2025.
What condition is Taylor CR RD over Grasshopper Creek 004 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2023.
How much traffic does Taylor CR RD over Grasshopper Creek 004 carry?
About 100 vehicles per day (2025 count), of which roughly 3% are trucks.
How long is Taylor CR RD over Grasshopper Creek 004?
The structure is 26 ft (7.8 m) long with a longest span of 25 ft (7.5 m) and a deck 20 ft wide.
Who owns Taylor CR RD over Grasshopper Creek 004?
It is owned by the County Highway Agency.