US Bridges

Fdr 130B over Slayton Creek

Good

Copiah County, Mississippi · No Data Entered · Structure no. 080704000014011

Built
2011
14 years old
Condition
Good
inspected February 2024
Type
Channel Beam
Concrete
Length
131 ft
3 main spans
Daily traffic
50
Owner
Federal
U.S. Forest Service

About this bridge

Fdr 130B over Slayton Creek is a concrete channel beam carrying Fdr 130B over Slayton Creek in Copiah County, Mississippi. It was built in 2011, so it is 14 years old, younger than the Mississippi average of 38.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 50 vehicles a day, projected to reach 75 by 2045. The structure is 131 ft (39.9 m) long and 24 ft wide. If it were closed, the detour would be 620.7 mi (999 km).

CarriesFdr 130B
CrossesSlayton Creek
LocationNo Data Entered
RouteFederal Lands Road 130B
Coordinates31.73043, -90.64777
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Last inspectionFebruary 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation6: Equal to present minimum criteria
Deck geometry6: Equal to present minimum criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating37.5 US tons
Inventory rating28.9 US tons

Structure

Structure typeChannel Beam
MaterialConcrete
DeckConcrete, precast panels
Main spans3 (+2 approach)
Design loadHL 93
Structure length131 ft (39.9 m)
Longest span31 ft (9.4 m)
Deck width24 ft (7.3 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic50 (—)
Projected traffic75 by 2045
Trucks—
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed620.7 mi (999 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerU.S. Forest Service
Maintained byU.S. Forest Service
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Fdr 130B over Slayton Creek built?

It was built in 2011, making it 14 years old in 2025.

What condition is Fdr 130B over Slayton Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2024.

How much traffic does Fdr 130B over Slayton Creek carry?

About 50 vehicles per day (latest count).

How long is Fdr 130B over Slayton Creek?

The structure is 131 ft (39.9 m) long with a longest span of 31 ft (9.4 m) and a deck 24 ft wide.

Who owns Fdr 130B over Slayton Creek?

It is owned by the U.S. Forest Service.