Camp No 3 Road over E Br Sturgeon River
GoodDickinson County, Michigan · 2.5 MI N of Hardwood · Structure no. 000000000002208
- Built
- 1988
- 37 years old
- Condition
- Good
- inspected September 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 45 ft
- 1 main span
- Daily traffic
- 44
- 2020 count
- Owner
- County
- County Highway Agency
About this bridge
Camp No 3 Road over E Br Sturgeon River is a prestressed concrete box beam or girders - multiple carrying Camp No 3 Road over E Br Sturgeon River in Dickinson County, Michigan. It was built in 1988, so it is 37 years old, younger than the Michigan average of 48.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 44 vehicles a day, roughly 24% of them trucks, projected to reach 48 by 2040. The structure is 45 ft (13.7 m) long and 25 ft wide. If it were closed, the detour would be 24.9 mi (40 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Camp No 3 Road over E Br Sturgeon River built?
It was built in 1988, making it 37 years old in 2025.
What condition is Camp No 3 Road over E Br Sturgeon River in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.
How much traffic does Camp No 3 Road over E Br Sturgeon River carry?
About 44 vehicles per day (2020 count), of which roughly 24% are trucks.
How long is Camp No 3 Road over E Br Sturgeon River?
The structure is 45 ft (13.7 m) long with a longest span of 40 ft (12.2 m) and a deck 25 ft wide.
Who owns Camp No 3 Road over E Br Sturgeon River?
It is owned by the County Highway Agency.