HWY Main ST over Water Wedge Pond Otlt
FairMiddlesex County, Massachusetts · Btn. Wedgepnd & RR · Structure no. W400192DBMUNNBI
- Built
- 1935
- 90 years old, rebuilt 1989
- Condition
- Fair
- inspected August 2023
- Type
- Slab
- Concrete
- Length
- 23 ft
- 1 main span
- Daily traffic
- 14,483
- 2019 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
HWY Main ST over Water Wedge Pond Otlt is a concrete slab carrying HWY Main ST over Water Wedge Pond Otlt in Middlesex County, Massachusetts. It was built in 1935 and reconstructed in 1989, so it is 90 years old, older than the Massachusetts average of 63.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 14,483 vehicles a day, roughly 6% of them trucks, projected to reach 38,377 by 2032. The structure is 23 ft (7 m) long and 62 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was HWY Main ST over Water Wedge Pond Otlt built?
It was built in 1935, making it 90 years old in 2025. It was reconstructed in 1989.
What condition is HWY Main ST over Water Wedge Pond Otlt in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in August 2023.
How much traffic does HWY Main ST over Water Wedge Pond Otlt carry?
About 14,483 vehicles per day (2019 count), of which roughly 6% are trucks.
How long is HWY Main ST over Water Wedge Pond Otlt?
The structure is 23 ft (7 m) long with a longest span of 20 ft (6.1 m) and a deck 62 ft wide.
Who owns HWY Main ST over Water Wedge Pond Otlt?
It is owned by the Town or Township Highway Agency.