US Bridges

HWY Ramp C over I 195

Good

Bristol County, Massachusetts · At E End of Braga Br · Structure no. F02110BMBDOTNBI

Built
2016
9 years old
Condition
Good
inspected November 2024
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
657 ft
5 main spans
Daily traffic
9,500
2024 count
Owner
State
State Highway Agency

About this bridge

HWY Ramp C over I 195 is a steel continuous stringer/multi-beam or girder carrying HWY Ramp C over I 195 in Bristol County, Massachusetts. It was built in 2016, so it is 9 years old, younger than the Massachusetts average of 63.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 9,500 vehicles a day, roughly 4% of them trucks. The structure is 657 ft (200.2 m) long and 31 ft wide.

CarriesHWY Ramp C
CrossesI 195
LocationAt E End of Braga Br
RouteInterstate 195
Coordinates41.70251, -71.15803
Functional classUrban Minor Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionNovember 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating46.4 US tons
Inventory rating35.7 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans5
Design loadHL 93
Structure length657 ft (200.2 m)
Longest span180 ft (54.9 m)
Deck width31 ft (9.6 m)
Roadway width28 ft (8.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic9,500 (2024)
Projected traffic—
Trucks4%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed—
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedOther structural work, including hydraulic replacements
Estimated improvement cost$1.9 million (2025 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was HWY Ramp C over I 195 built?

It was built in 2016, making it 9 years old in 2025.

What condition is HWY Ramp C over I 195 in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2024.

How much traffic does HWY Ramp C over I 195 carry?

About 9,500 vehicles per day (2024 count), of which roughly 4% are trucks.

How long is HWY Ramp C over I 195?

The structure is 657 ft (200.2 m) long with a longest span of 180 ft (54.9 m) and a deck 31 ft wide.

Who owns HWY Ramp C over I 195?

It is owned by the State Highway Agency.