US Bridges

HWY Ramp G over Comb Central ST & Macrr

Good

Bristol County, Massachusetts · I 195 WB to 79 NB · Structure no. F02104BHCDOTNBI

Built
2016
9 years old
Condition
Good
inspected November 2022
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
690 ft
6 main spans
Daily traffic
7,300
2022 count
Owner
State
State Highway Agency

About this bridge

HWY Ramp G over Comb Central ST & Macrr is a steel continuous stringer/multi-beam or girder carrying HWY Ramp G over Comb Central ST & Macrr in Bristol County, Massachusetts. It was built in 2016, so it is 9 years old, younger than the Massachusetts average of 63.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 7,300 vehicles a day, roughly 9% of them trucks. The structure is 690 ft (210.3 m) long and 26 ft wide. If it were closed, the detour would be 1.9 mi (3 km).

CarriesHWY Ramp G
CrossesComb Central ST & Macrr
LocationI 195 WB to 79 NB
RouteInterstate 195
Coordinates41.70372, -71.15956
Functional classUrban Principal Arterial - Other Freeway or Expressway

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionNovember 2022
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry6: Equal to present minimum criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating46.4 US tons
Inventory rating35.7 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans6
Design loadHL 93
Structure length690 ft (210.3 m)
Longest span150 ft (45.7 m)
Deck width26 ft (7.8 m)
Roadway width22 ft (6.7 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic7,300 (2022)
Projected traffic—
Trucks9%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway and railroad
Detour if closed1.9 mi (3 km)
TollOn a free road
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedWidening of existing bridge without deck rehabilitation
Estimated improvement cost$5.9 million (2025 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was HWY Ramp G over Comb Central ST & Macrr built?

It was built in 2016, making it 9 years old in 2025.

What condition is HWY Ramp G over Comb Central ST & Macrr in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2022.

How much traffic does HWY Ramp G over Comb Central ST & Macrr carry?

About 7,300 vehicles per day (2022 count), of which roughly 9% are trucks.

How long is HWY Ramp G over Comb Central ST & Macrr?

The structure is 690 ft (210.3 m) long with a longest span of 150 ft (45.7 m) and a deck 26 ft wide.

Who owns HWY Ramp G over Comb Central ST & Macrr?

It is owned by the State Highway Agency.