TR 60E Brenton over North Fork Vermilion
FairFord County, Illinois · 2130N 1600E · Structure no. 027323200000000
- Built
- 1975
- 50 years old
- Condition
- Fair
- inspected April 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 52 ft
- 1 main span
- Daily traffic
- 25
- 2023 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
TR 60E Brenton over North Fork Vermilion is a prestressed concrete box beam or girders - multiple carrying TR 60E Brenton over North Fork Vermilion in Ford County, Illinois. It was built in 1975, so it is 50 years old, older than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 25 vehicles a day, projected to reach 25 by 2046. The structure is 52 ft (15.8 m) long and 27 ft wide. If it were closed, the detour would be 5 mi (8 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was TR 60E Brenton over North Fork Vermilion built?
It was built in 1975, making it 50 years old in 2025.
What condition is TR 60E Brenton over North Fork Vermilion in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2023.
How much traffic does TR 60E Brenton over North Fork Vermilion carry?
About 25 vehicles per day (2023 count).
How long is TR 60E Brenton over North Fork Vermilion?
The structure is 52 ft (15.8 m) long with a longest span of 51 ft (15.5 m) and a deck 27 ft wide.
Who owns TR 60E Brenton over North Fork Vermilion?
It is owned by the Town or Township Highway Agency.