Plum Grove RD over Salt Creek
FairCook County, Illinois · 0.4 M N Ill 62 P18 · Structure no. 016304800000000
- Built
- 1957
- 68 years old
- Condition
- Fair
- inspected June 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 57 ft
- 1 main span
- Daily traffic
- 2,300
- 2022 count
- Owner
- County
- County Highway Agency
About this bridge
Plum Grove RD over Salt Creek is a steel stringer/multi-beam or girder carrying Plum Grove RD over Salt Creek in Cook County, Illinois. It was built in 1957, so it is 68 years old, older than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 2,300 vehicles a day, roughly 3% of them trucks, projected to reach 2,323 by 2046. The structure is 57 ft (17.3 m) long and 36 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Plum Grove RD over Salt Creek built?
It was built in 1957, making it 68 years old in 2025.
What condition is Plum Grove RD over Salt Creek in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2024.
How much traffic does Plum Grove RD over Salt Creek carry?
About 2,300 vehicles per day (2022 count), of which roughly 3% are trucks.
How long is Plum Grove RD over Salt Creek?
The structure is 57 ft (17.3 m) long with a longest span of 53 ft (16.2 m) and a deck 36 ft wide.
Who owns Plum Grove RD over Salt Creek?
It is owned by the County Highway Agency.