US Bridges

2100 East Road over S. Gooding Main Canal

Good

Gooding County, Idaho · 0.9 S. 2.0 E. Gooding · Structure no. 000000000024476

Built
2024
1 years old
Condition
Good
inspected June 2024
Type
Stringer/Multi-beam or Girder
Steel
Length
45 ft
1 main span
Daily traffic
70
2024 count
Owner
Local
Other Local Agency

About this bridge

2100 East Road over S. Gooding Main Canal is a steel stringer/multi-beam or girder carrying 2100 East Road over S. Gooding Main Canal in Gooding County, Idaho. It was built in 2024, so it is 1 years old, younger than the Idaho average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 9 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 70 vehicles a day, roughly 5% of them trucks, projected to reach 105 by 2042. The structure is 45 ft (13.7 m) long and 36 ft wide. If it were closed, the detour would be 1.9 mi (3 km).

Carries2100 East Road
CrossesS. Gooding Main Canal
Location0.9 S. 2.0 E. Gooding
RouteCounty Highway 0
StateIdaho
Coordinates42.92439, -114.67325
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck9 ExcellentNo problems noted.
Superstructure9 ExcellentNo problems noted.
Substructure9 ExcellentNo problems noted.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionJune 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation9: Superior to present desirable criteria
Deck geometry9: Superior to present desirable criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating46 US tons
Inventory rating36 US tons

Structure

MaterialSteel
DeckCorrugated steel
Main spans1
Design loadHL 93
Structure length45 ft (13.7 m)
Longest span41 ft (12.6 m)
Deck width36 ft (11 m)
Roadway width36 ft (11 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic70 (2024)
Projected traffic105 by 2042
Trucks5%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed1.9 mi (3 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerOther Local Agency
Maintained byOther Local Agency
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was 2100 East Road over S. Gooding Main Canal built?

It was built in 2024, making it 1 years old in 2025.

What condition is 2100 East Road over S. Gooding Main Canal in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.

How much traffic does 2100 East Road over S. Gooding Main Canal carry?

About 70 vehicles per day (2024 count), of which roughly 5% are trucks.

How long is 2100 East Road over S. Gooding Main Canal?

The structure is 45 ft (13.7 m) long with a longest span of 41 ft (12.6 m) and a deck 36 ft wide.

Who owns 2100 East Road over S. Gooding Main Canal?

It is owned by the Other Local Agency.