STC6870;PAHSIMEROI over Big Creek Fish Passage
GoodCuster County, Idaho · 9.0 S. 10.4 E. May · Structure no. 000000000034633
- Built
- 2014
- 11 years old
- Condition
- Good
- inspected April 2021
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 50 ft
- 1 main span
- Daily traffic
- 30
- 2023 count
- Owner
- County
- County Highway Agency
About this bridge
STC6870;PAHSIMEROI over Big Creek Fish Passage is a steel stringer/multi-beam or girder carrying STC6870;PAHSIMEROI over Big Creek Fish Passage in Custer County, Idaho. It was built in 2014, so it is 11 years old, younger than the Idaho average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 30 vehicles a day, roughly 50% of them trucks, projected to reach 45 by 2042. The structure is 50 ft (15.2 m) long and 24 ft wide. If it were closed, the detour would be 42.3 mi (68 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was STC6870;PAHSIMEROI over Big Creek Fish Passage built?
It was built in 2014, making it 11 years old in 2025.
What condition is STC6870;PAHSIMEROI over Big Creek Fish Passage in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2021.
How much traffic does STC6870;PAHSIMEROI over Big Creek Fish Passage carry?
About 30 vehicles per day (2023 count), of which roughly 50% are trucks.
How long is STC6870;PAHSIMEROI over Big Creek Fish Passage?
The structure is 50 ft (15.2 m) long with a longest span of 48 ft (14.6 m) and a deck 24 ft wide.
Who owns STC6870;PAHSIMEROI over Big Creek Fish Passage?
It is owned by the County Highway Agency.