Big Bend Road over Parker Creek;morter Br
FairBoundary County, Idaho · 1.5 N. 4.8 W. Copeland · Structure no. 000000000030390
- Built
- 1983
- 42 years old
- Condition
- Fair
- inspected June 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 85 ft
- 3 main spans
- Daily traffic
- 30
- 2023 count
- Owner
- County
- County Highway Agency
About this bridge
Big Bend Road over Parker Creek;morter Br is a steel continuous stringer/multi-beam or girder carrying Big Bend Road over Parker Creek;morter Br in Boundary County, Idaho. It was built in 1983, so it is 42 years old, younger than the Idaho average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 30 vehicles a day, roughly 50% of them trucks, projected to reach 45 by 2042. The structure is 85 ft (25.9 m) long and 18 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Big Bend Road over Parker Creek;morter Br built?
It was built in 1983, making it 42 years old in 2025.
What condition is Big Bend Road over Parker Creek;morter Br in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in June 2024.
How much traffic does Big Bend Road over Parker Creek;morter Br carry?
About 30 vehicles per day (2023 count), of which roughly 50% are trucks.
How long is Big Bend Road over Parker Creek;morter Br?
The structure is 85 ft (25.9 m) long with a longest span of 34 ft (10.4 m) and a deck 18 ft wide.
Who owns Big Bend Road over Parker Creek;morter Br?
It is owned by the County Highway Agency.