Ramp Es over FAI-H1(HALAWA Ic #6)
GoodHonolulu County, Hawaii · 0.074MI S/Struct #2 · Structure no. 003000H10201340
- Built
- 1974
- 51 years old
- Condition
- Good
- inspected March 2023
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete Continuous
- Length
- 804 ft
- 8 main spans
- Daily traffic
- 110,500
- 2017 count
- Owner
- State
- State Highway Agency
About this bridge
Ramp Es over FAI-H1(HALAWA Ic #6) is a prestressed concrete continuous stringer/multi-beam or girder carrying Ramp Es over FAI-H1(HALAWA Ic #6) in Honolulu County, Hawaii. It was built in 1974, so it is 51 years old, younger than the Hawaii average of 63.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 110,500 vehicles a day, roughly 4% of them trucks, projected to reach 166,683 by 2025. The structure is 804 ft (245.1 m) long and 35 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ramp Es over FAI-H1(HALAWA Ic #6) built?
It was built in 1974, making it 51 years old in 2025.
What condition is Ramp Es over FAI-H1(HALAWA Ic #6) in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2023.
How much traffic does Ramp Es over FAI-H1(HALAWA Ic #6) carry?
About 110,500 vehicles per day (2017 count), of which roughly 4% are trucks.
How long is Ramp Es over FAI-H1(HALAWA Ic #6)?
The structure is 804 ft (245.1 m) long with a longest span of 105 ft (32 m) and a deck 35 ft wide.
Who owns Ramp Es over FAI-H1(HALAWA Ic #6)?
It is owned by the State Highway Agency.