US Bridges

SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps

Good

Fulton County, Georgia · In Atlanta · Structure no. 000000012107210

Built
1988
37 years old
Condition
Good
inspected May 2023
Type
Box Beam or Girders - Single or Spread
Prestressed Concrete Continuous
Length
562 ft
3 main spans
Daily traffic
6,805
2024 count
Owner
State
State Highway Agency

About this bridge

SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps is a prestressed concrete continuous box beam or girders - single or spread carrying SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps in Fulton County, Georgia. It was built in 1988, so it is 37 years old, younger than the Georgia average of 47.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 6,805 vehicles a day, roughly 1% of them trucks, projected to reach 6,960 by 2032. The structure is 562 ft (171.3 m) long and 69 ft wide. If it were closed, the detour would be 3.1 mi (5 km).

CarriesSR10R Wbl to M9155
CrossesI-75 + 3 I-75 Ramps
LocationIn Atlanta
RouteState Highway 10
StateGeorgia
Coordinates33.75988, -84.37998
Functional classUrban Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionMay 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating50.9 US tons
Inventory rating35.9 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans3
Design loadHS 20 + Mod
Structure length562 ft (171.3 m)
Longest span190 ft (57.9 m)
Deck width69 ft (21.1 m)
Roadway width66 ft (20.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic6,805 (2024)
Projected traffic6,960 by 2032
Trucks1%
Lanes on structure4
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed3.1 mi (5 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps built?

It was built in 1988, making it 37 years old in 2025.

What condition is SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in May 2023.

How much traffic does SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps carry?

About 6,805 vehicles per day (2024 count), of which roughly 1% are trucks.

How long is SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps?

The structure is 562 ft (171.3 m) long with a longest span of 190 ft (57.9 m) and a deck 69 ft wide.

Who owns SR10R Wbl to M9155 over I-75 + 3 I-75 Ramps?

It is owned by the State Highway Agency.