I-75SB Ramp H-12 over Snake Creek (C-9) Canal
GoodBroward County, Florida · At Dade County Line · Structure no. 860679
- Built
- 2018
- 7 years old
- Condition
- Good
- inspected August 2024
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete
- Length
- 204 ft
- 3 main spans
- Daily traffic
- 24,500
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
I-75SB Ramp H-12 over Snake Creek (C-9) Canal is a prestressed concrete stringer/multi-beam or girder carrying I-75SB Ramp H-12 over Snake Creek (C-9) Canal in Broward County, Florida. It was built in 2018, so it is 7 years old, younger than the Florida average of 41.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 24,500 vehicles a day, roughly 5% of them trucks, projected to reach 42,508 by 2042. The structure is 204 ft (62.2 m) long and 59 ft wide.
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I-75SB Ramp H-12 over Snake Creek (C-9) Canal built?
It was built in 2018, making it 7 years old in 2025.
What condition is I-75SB Ramp H-12 over Snake Creek (C-9) Canal in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.
How much traffic does I-75SB Ramp H-12 over Snake Creek (C-9) Canal carry?
About 24,500 vehicles per day (2024 count), of which roughly 5% are trucks.
How long is I-75SB Ramp H-12 over Snake Creek (C-9) Canal?
The structure is 204 ft (62.2 m) long with a longest span of 71 ft (21.5 m) and a deck 59 ft wide.
Who owns I-75SB Ramp H-12 over Snake Creek (C-9) Canal?
It is owned by the State Highway Agency.