Ramp to I 25 Sbnd over Clear Creek R
GoodAdams County, Colorado · .2 MI N I76; .1 MI W I25 · Structure no. E-17-NY
- Built
- 1992
- 33 years old
- Condition
- Good
- inspected June 2023
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete Continuous
- Length
- 316 ft
- 3 main spans
- Daily traffic
- 121,000
- 2020 count
- Owner
- State
- State Highway Agency
About this bridge
Ramp to I 25 Sbnd over Clear Creek R is a prestressed concrete continuous box beam or girders - single or spread carrying Ramp to I 25 Sbnd over Clear Creek R in Adams County, Colorado. It was built in 1992, so it is 33 years old, younger than the Colorado average of 42.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 121,000 vehicles a day, roughly 10% of them trucks, projected to reach 141,570 by 2040. The structure is 316 ft (96.2 m) long and 67 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ramp to I 25 Sbnd over Clear Creek R built?
It was built in 1992, making it 33 years old in 2025.
What condition is Ramp to I 25 Sbnd over Clear Creek R in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2023.
How much traffic does Ramp to I 25 Sbnd over Clear Creek R carry?
About 121,000 vehicles per day (2020 count), of which roughly 10% are trucks.
How long is Ramp to I 25 Sbnd over Clear Creek R?
The structure is 316 ft (96.2 m) long with a longest span of 103 ft (31.5 m) and a deck 67 ft wide.
Who owns Ramp to I 25 Sbnd over Clear Creek R?
It is owned by the State Highway Agency.