US Bridges

80 WB Off Ramp over 4th Street

Good

San Francisco County, California · 04-SF-080-4.97-SF · Structure no. 34 0129C

Built
2008
17 years old
Condition
Good
inspected March 2023
Type
Box Beam or Girders - Single or Spread
Prestressed Concrete Continuous
Length
556 ft
8 main spans
Daily traffic
19,700
2013 count
Owner
State
State Highway Agency

About this bridge

80 WB Off Ramp over 4th Street is a prestressed concrete continuous box beam or girders - single or spread carrying 80 WB Off Ramp over 4th Street in San Francisco County, California. It was built in 2008, so it is 17 years old, younger than the California average of 54.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 19,700 vehicles a day, roughly 10% of them trucks, projected to reach 50,000 by 2040. The structure is 556 ft (169.5 m) long and 37 ft wide. If it were closed, the detour would be 0.6 mi (1 km).

Carries80 WB Off Ramp
Crosses4th Street
Location04-SF-080-4.97-SF
RouteInterstate 80
Coordinates37.77918, -122.40024
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionMarch 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry6: Equal to present minimum criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating59.6 US tons
Inventory rating35.7 US tons

Structure

MaterialPrestressed Concrete Continuous
DeckConcrete, cast-in-place
Main spans8
Design loadHS 20 + Mod
Structure length556 ft (169.5 m)
Longest span137 ft (41.8 m)
Deck width37 ft (11.4 m)
Roadway width37 ft (11.4 m)
Vertical clearance over deck17 ft (5.1 m)

Traffic and service

Average daily traffic19,700 (2013)
Projected traffic50,000 by 2040
Trucks10%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesHighway
Detour if closed0.6 mi (1 km)
TollToll bridge
National Highway SystemYes
Strategic Highway NetworkInterstate STRAHNET route

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNot applicable (no waterway)

Frequently asked questions

When was 80 WB Off Ramp over 4th Street built?

It was built in 2008, making it 17 years old in 2025.

What condition is 80 WB Off Ramp over 4th Street in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2023.

How much traffic does 80 WB Off Ramp over 4th Street carry?

About 19,700 vehicles per day (2013 count), of which roughly 10% are trucks.

How long is 80 WB Off Ramp over 4th Street?

The structure is 556 ft (169.5 m) long with a longest span of 137 ft (41.8 m) and a deck 37 ft wide.

Who owns 80 WB Off Ramp over 4th Street?

It is owned by the State Highway Agency.