Poway Road over Pomerado Creek
GoodSan Diego County, California · 0.1M W/O Pomerado RD · Structure no. 57C0280
- Built
- 1951
- 74 years old, rebuilt 1964
- Condition
- Good
- inspected October 2024
- Type
- Culvert
- Concrete
- Length
- 48 ft
- 3 main spans
- Daily traffic
- 30,900
- 2020 count
- Owner
- City
- City or Municipal Highway Agency
About this bridge
Poway Road over Pomerado Creek is a concrete culvert carrying Poway Road over Pomerado Creek in San Diego County, California. It was built in 1951 and reconstructed in 1964, so it is 74 years old, older than the California average of 54.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 30,900 vehicles a day, roughly 4% of them trucks, projected to reach 32,930 by 2042. The structure is 48 ft (14.6 m) long and 94 ft wide. If it were closed, the detour would be 1.2 mi (2 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
| Culvert | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Poway Road over Pomerado Creek built?
It was built in 1951, making it 74 years old in 2025. It was reconstructed in 1964.
What condition is Poway Road over Pomerado Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2024.
How much traffic does Poway Road over Pomerado Creek carry?
About 30,900 vehicles per day (2020 count), of which roughly 4% are trucks.
How long is Poway Road over Pomerado Creek?
The structure is 48 ft (14.6 m) long with a longest span of 14 ft (4.2 m) and a deck 94 ft wide.
Who owns Poway Road over Pomerado Creek?
It is owned by the City or Municipal Highway Agency.